reduction in overall hours
reduction in existing footprint
Streamlined operating procedures and clearer communication across overhaul teams.
A tier-one supplier won a key contract to deliver a major bogie overhaul program for an entire regional passenger train fleet. A number of issues during mobilization — including a lack of engineering information, unclear quality specifications, poor workplace organization and internal logistics — led to delays in program delivery. Our team was engaged to accelerate delivery and establish a streamlined overhaul line and processes.
Based on initial reviews and observations, a recovery plan was developed with cross-functional stakeholders across the value stream, and governance meetings were initiated to resolve or escalate any risks or concerns in a timely manner.
Shop layout was changed using Lean workplace-organization principles, ensuring material flow to and from the point of use. Standard process steps and times were established — including safety, quality and ‘knacks’ requirements — with input from highly experienced line workers.
Overhaul build plans were developed and visualized on short-interval control boards to improve progress visibility and communication within teams.